Keeping Lynchburg Regional Airport Safe & Efficient
Lynchburg Regional Airport (LYH) is committed to ensuring safe, reliable, and efficient air service for our community. As part of this commitment, we are undertaking a vital rehabilitation project for Runway 4-22, our primary runway for air carrier operations. This project is crucial to maintaining the safety and efficiency of the airport, improving the flying experience for passengers, and supporting airline needs.
Runway 4-22, measuring 7,100 feet by 150 feet, is essential for daily commercial flight operations at LYH. Over time, runways, like roads, require periodic maintenance, including asphalt replacement. However, unlike roads, a runway must be fully closed for repairs. The rehabilitation includes full-length pavement repairs, grade corrections to smooth the runway, and an upgrade to the lighting system with new, brighter, and more energy-efficient LED lights. These improvements will extend the runway’s lifespan, enhance safety for pilots, and improve operational efficiency at the airport.
This project is funded through the Airport Improvement Program (AIP), a Federal Aviation Administration (FAA) initiative that helps support infrastructure upgrades at airports across the country. The AIP ensures that airports like LYH remain safe and efficient, supporting both local air travel and economic growth.
For more details about the AIP, visit the FAA’s Airport Improvement Program page.
Traveler Impact
While we strive to minimize disruptions, there will be temporary flight schedule adjustments to accommodate construction work. To reduce the impact on daily flights, much of the rehabilitation work will occur during night hours and extended weekends.
Construction Schedule:
- Summer Phase: June 1 – August 30, 2025
- Fall Phase: September 1 – September 25, 2025
Flight Schedule Adjustments:
- Weekdays: Flights will operate up to 12:00 AM (midnight) and after 5:00 AM
- Weekends:
- Saturday: Flights before 12:00 PM (Noon)
- Sunday: Flights after 12:00 PM (Noon), and after 5:00 AM (Sept. 14,21,28)
For real-time flight schedules and bookings, visit American Airlines.
Project Timeline
Milestone | Date |
BID Process Begins | May 24, 2024 |
Construction Begins | June 1, 2025 |
Summer Phase Ends | August 30, 2025 |
Fall Phase Begins | September 1, 2025 |
Targeted Project Completion | September 25, 2025 |
We appreciate your patience and support as we work to enhance Lynchburg Regional Airport for the future. These improvements will ensure that LYH remains a safe, modern, and efficient gateway for travelers.
For updates, check back here or follow us on social media.